Please follow the steps below to generate a schedule report for a project:
1. Go to the Reports tab on your account
2. Select Presentation in the "Report Type" drop down
- You will need to select a project and a specific schedule within that project
3. Then select a presentation and fold within that presentation
- You will be able to choose to run either a Presentation Log or Presentation Picks report
4. Select the View Report button